The CLT frame was originally scheduled to be assembled on week 50, 2020. It was postponed to week 1, 2021 and again postponed and finally assembled on week 3, 2021.

Nevertheless, this was certainly the most exciting and action packed part of the journey so far. Amazing to see the walls, roof, weatherproofing membranes go up in a span of few days. A lot of good things and some not so good things.

My previous articles at

  1. My house build journey : Location
  2. My house build journey : Design
  3. My house build journey : Building permit
  4. My house build journey : Technical Consultation
  5. My house build journey : Stalled by Bank Bureaucracy
  6. My house build journey: Start Message
  7. My house build journey: Foundation

We needed some preparations to be done before the CLT installation.

  • Electricity connection (El anslutning): Mostly, everyone uses this ByggStröm (Construction electricity) for the time of the construction.

--

--